CBR PLUS soil stabilization can be applied to various kinds of roads, namely:
![]() Step 1 Soil Analysis and anticipated Traffic Loading The local soil from the proposed project has to classified in terms of either AASHTO or the Unified Classification System. This is done by means of sieve analysis and the Atterberg Limits test. The proposed traffic loading for the road has to be determined. CBR PLUS will further analyze the soil for reactivity with the CBR PLUS product, to ensure compatibility and determine the correct application or dosage rate for the particular soil to be treated. All soils are different and react differently with the CBR PLUS. This test ensures the optimum application rate for each soil type and also ensures highest performance possible. ![]() Step 2 Design the Road The information from Step 1 is used to design the proposed road and the appropriate construction method is prescribed. This would include the construction sequence, number of layers required in the road, equipment to be used, additional material such as clay or gravel that has to be added to modify the soil and post construction monitoring and treatment. All recommendations are based on road layers 150 mm or 6 inches thick. Step 3 Equipment Required: ![]() For most methods of construction, the machinery equipment required is listed as follows: Table 4.1 List of Machinery needed for Construction
Average daily production is about 300 to 750 meter length x 7-9 meter width x 15 cm thickness or about 1.2 km - 1.5 km / week. (i.e., 2,000 - 5,000m2 / day or 10,000 - 25,000 m2/week). Step 4 Construction Procedure
Step 5 Opening to Traffic During construction and immediately after final compaction, the roadway can be opened to traffic. Any deformation should be corrected by grading and compaction before the material dries out fully. Step 6 Curing After the stabilized layer has been compacted to the required density and brought to the required lines and grades in accordance with the typical cross section, the completed section should be cured. This curing is accomplished by the daily application of water with the water tanker, depending upon the climate and the depth of treatment, usually for seven to ten days after completion date. During this period traffic may use the stabilized road. Please note that during this period small quantities of CBR PLUS remain on the surface which may create a slippery face in some instances during rainfall and depending upon the type of soil stabilized. This slipperiness is normal and usually disappears after the curing period or a few rainstorms. Step 7 Maintenance One of the major advantages of CBR PLUS over other soil stabilizers is the fact that CBR PLUS can be repaired.
If untreated material from the road side is brought onto the road during maintenance grading, the surface should be treated with a very small dosage of CBR PLUS. Step 8 Surfacing If surfacing of the treated road surface is required, the field moisture content of the stabilized layer must be allowed to stabilize between 50 to 60 % of optimum moisture content. Depending on the soil type, climate and temperature (including rainfall during this curing period), this may take between 6 to 12 weeks or longer. Step 9 Life span of CBR PLUS Stabilized Layer The change in the treated clay is permanent and will not reverse itself due to leaching. In theory therefore, the CBR PLUS treated road should last forever if the construction procedure and instructions are followed properly, but in reality special variability of subsoil and drainage is expected. Normal wear and tear prevails and the roads built with CBR PLUS stabilized soil will require some maintenance. The resultant road should however present a significantly improved rideability, particularly in wet weather, and substantial reductions in maintenance. There are some CBR PLUS stabilized roads in existence, which have been used continuously for over twenty years. |
| Copyright 2003-2004 CBR PLUS North America Inc. All rights reserved. Contact CBR PLUS North America Inc. |
| 3D Animated Flags--By 3DFlags.com |
HOME | COMPANY | PRODUCT | APPLICATION | TECHNICAL | BROCHURE | PROJECTS | CONTACT US | ASSOCIATES |